
Total number of projects: 3
As coordinator: 0
As participant: 3
Sole participant: 0
Coordinator / Participant Ratio: 0*
| Total project funding [€]: | Projects [No]: | |||||
|---|---|---|---|---|---|---|
| Year: | coordinator* | participant* | per partner | as coordinator | as participant | |
| 2017 | 0 | 11.186.578 | 394.414 | 2 | ||
| 2016 | 0 | 6.477.596 | 0 | 1 | ||
Total number of partners: 58
Partner loyalty:
Frequent Partner: (> 2 projects): 3
Rare Partner: 55
Frequent / Rare Partner Ratio: 0.05
| Start date | Project | acronym | role | funding | partners |
|---|---|---|---|---|---|
| 2017-10-01 | Annular Instabilities and Transient Phenomena in Gas Turbine Combustors | ANNULIGhT | participant | 3.974.483 | 10 |
| 2017-10-01 | TURBOmachinery REtrofits enabling FLEXible back-up capacity for the transition of the European energy system | TURBO-REFLEX | participant | 7.212.095 | 26 |
| 2016-01-01 | Flexible Fossil Power Plants for the Future Energy Market through new and advanced Turbine Technologies | FLEXTURBINE | participant | 6.477.596 | 25 |